CLIENT:

Exel Walsh Western


LOCATION:

Western Business Pk, Oak Rd Knockmitten, Dublin 12


PROJECT:

Exel Walsh Western Warehouse / 28,000 sqm


This facility was the first high bay, narrow aisle warehouse built in Ireland. It was designed with a super flat floor to facilitate wire guided fork trucks. In addition to the 24 standard dock levellers, the facility is fitted with 2 cross dock (transfer) piers. The facility was constructed in three phases, is 28,000sqm and has a 15m clear eaves height internally. The visual mass of the high bay warehouse is reduced by the use of flat and profiled cladding. The building's bulk is reduced through the use of silver and red cladding.

The office accommodation is provided in 3 no. blocks which are located on the corners of the warehouse. This future proofs the facility should it be required to serve a number of smaller operators.